| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Setup Business Accounts | 12 days | Wed 3/1/00 | Thu 3/16/00 | | 0% |
| 2 | Visit MSU Foundation | 6 days | Wed 3/1/00 | Wed 3/8/00 | willoughby,Lee | 0% |
| 3 | Visit MSU Funded Projects | 6 days | Thu 3/9/00 | Thu 3/16/00 | Lee,willoughby | 0% |
| 4 | Literature Search (Motor Cooling) | 152 days | Fri 3/17/00 | Mon 10/16/00 | | 7% |
| 5 | WEB | 3.38 days | Fri 3/17/00 | Thu 3/30/00 | jack,Ylui | 0% |
| 6 | JHU Library | 6 days | Fri 3/17/00 | Fri 3/24/00 | willoughby | 0% |
| 7 | MSU Library | 5.25 days | Fri 3/17/00 | Fri 3/24/00 | Ylui,jack | 0% |
| 8 | U of Md. Library | 5.25 days | Fri 3/17/00 | Fri 3/24/00 | Ylui,jack | 0% |
| 9 | Government Agencies | 6 days | Fri 3/17/00 | Fri 3/24/00 | willoughby | 0% |
| 10 | Acquisition Processing | 1 day | Wed 5/24/00 | Wed 5/24/00 | | 0% |
| 11 | Purchase CFX Tasc Flow | 1 day | Wed 5/24/00 | Wed 5/24/00 | willoughby,Lee | 0% |
| 12 | Purchase Fluent | 1 day | Wed 5/24/00 | Wed 5/24/00 | willoughby,Lee | 0% |
| 13 | Purchase Bladegen Turbogen | 1 day | Wed 5/24/00 | Wed 5/24/00 | willoughby,Lee | 0% |
| 14 | Purchase Catia 4.2 | 1 day | Wed 5/24/00 | Wed 5/24/00 | willoughby,Lee | 0% |
| 15 | MSU TRAINING | 99 days | Wed 5/31/00 | Mon 10/16/00 | | 19% |
| 16 | Flotran Training | 4.5 days | Wed 5/31/00 | Tue 6/6/00 | willoughby,Doss | 0% |
| 17 | ANSYS | 8 days | Thu 10/5/00 | Mon 10/16/00 | willoughby,Doss | 0% |
| 18 | Fluent Training | 5 days | Wed 5/31/00 | Tue 6/6/00 | Lee | 100% |
| 19 | CFX Tasc Flow Training | 5 days | Mon 7/31/00 | Fri 8/4/00 | Doss,Lee | 0% |
| 20 | Blade Gen Training | 4 days | Tue 9/26/00 | Fri 9/29/00 | Lee,Doss | 0% |
| 21 | MSU and B&D FTP Testing | 28 days | Fri 6/2/00 | Tue 7/11/00 | | 0% |
| 22 | Transfer Files To MSU | 6 days | Fri 6/2/00 | Fri 6/9/00 | willoughby,Tanorah | 0% |
| 23 | | 6 days | Mon 7/3/00 | Mon 7/10/00 | willoughby,jack | 0% |
| 24 | Student CFD Development | 1 day | Mon 7/10/00 | Tue 7/11/00 | willoughby,Doss,Lee | 0% |
| 25 | List/Install Theoretical Needs | 12 days | Fri 5/12/00 | Mon 5/29/00 | | 0% |
| 26 | Flotran | 7.2 days | Fri 5/12/00 | Mon 5/29/00 | Team,Lee,willoughby,Doss | 0% |
| 27 | IBM Catia 4.2 | 12 days | Fri 5/12/00 | Mon 5/29/00 | Lee,willoughby,Doss | 0% |
| 28 | CFX TASC FLOW ,BG | 12 days | Fri 5/12/00 | Mon 5/29/00 | Lee,willoughby,Doss | 0% |
| 29 | Ensight | 12 days | Fri 5/12/00 | Mon 5/29/00 | Lee,willoughby,Doss | 0% |
| 30 | List/Install Experimental Needs | 8.5 days | Wed 5/24/00 | Mon 6/5/00 | | 0% |
| 31 | Swirl machine particle trace | 2.5 days | Tue 5/30/00 | Thu 6/1/00 | Lee,Ylui | 0% |
| 32 | Analization Chamber | 8 days | Wed 5/24/00 | Fri 6/2/00 | Lee,Ylui | 0% |
| 33 | Three Dimensional LAG Geometry | 1.5 days | Fri 6/2/00 | Mon 6/5/00 | Lee,Ylui | 0% |
| 34 | Software Analysis | 371 days | Mon 6/19/00 | Mon 11/19/01 | | 0% |
| 35 | Set-Up Of Two-D Simulation | 1 day | Fri 9/1/00 | Fri 9/1/00 | Team | 0% |
| 36 | Develop X-SEC. Surface | 6 days | Mon 6/19/00 | Fri 10/6/00 | Team | 0% |
| 37 | Mesh 2-D Geometry | 2 days | Wed 9/27/00 | Thu 9/28/00 | Team | 0% |
| 38 | Postprocess With Solver | 3 days | Wed 10/4/00 | Fri 10/6/00 | Team | 0% |
| 39 | Analize/Compare Results | 1 day | Mon 10/9/00 | Mon 10/9/00 | Team | 0% |
| 40 | Set-Up Of Three-D Simulation | 14 days | Tue 10/10/00 | Fri 10/27/00 | Team | 0% |
| 41 | Develop Geometry Full Body | 1 day | Mon 10/29/01 | Mon 10/29/01 | Team | 0% |
| 42 | Mesh 3-D Geometry | 5 days | Mon 11/6/00 | Fri 11/10/00 | Team | 0% |
| 43 | Postprocess With Solver | 5 days | Mon 11/13/00 | Fri 11/17/00 | Team | 0% |
| 44 | Analize/Compare Results | 1 day | Mon 11/19/01 | Mon 11/19/01 | Team | 0% |
| 45 | Hardware Analysis | 14 days | Tue 11/21/00 | Fri 12/8/00 | | 0% |
| 46 | Evaluate System Solution Options | 3 days | Tue 11/21/00 | Thu 11/23/00 | Team | 0% |
| 47 | Clear Housing Prototypes Delivered(MSU) | 1 day | Tue 11/21/00 | Tue 11/21/00 | Team | 0% |
| 48 | LDPA Prototype | 3 days | Mon 11/27/00 | Wed 11/29/00 | Team | 0% |
| 49 | PIV Prototype | 2 days | Tue 11/28/00 | Wed 11/29/00 | Team | 0% |
| 50 | Calculate Airflow and Heat Transfer | 1 day | Thu 11/30/00 | Thu 11/30/00 | Team | 0% |
| 51 | Compare Experimentaion With CFD Output Models | 6 days | Fri 12/1/00 | Fri 12/8/00 | Team | 0% |
| 52 | Literature Search On Power Tool | 10 days | Mon 12/11/00 | Fri 12/22/00 | | 0% |
| 53 | Noise/Vibration | 5 days | Mon 12/11/00 | Fri 12/15/00 | Team | 0% |
| 54 | Particulate Flow | 5 days | Mon 12/18/00 | Fri 12/22/00 | Team | 0% |
|