bandd.dat





Project Start:
Project Finish:
Wed 3/1/00
Mon 11/19/01


Tasks


IDTask NameDurationStartFinishResource Names% Complete
1Setup Business Accounts12 daysWed 3/1/00Thu 3/16/00 0%
2Visit MSU Foundation6 daysWed 3/1/00Wed 3/8/00willoughby,Lee0%
3Visit MSU Funded Projects6 daysThu 3/9/00Thu 3/16/00Lee,willoughby0%
4Literature Search (Motor Cooling)152 daysFri 3/17/00Mon 10/16/00 7%
5WEB3.38 daysFri 3/17/00Thu 3/30/00jack,Ylui0%
6JHU Library6 daysFri 3/17/00Fri 3/24/00willoughby0%
7MSU Library5.25 daysFri 3/17/00Fri 3/24/00Ylui,jack0%
8U of Md. Library5.25 daysFri 3/17/00Fri 3/24/00Ylui,jack0%
9Government Agencies6 daysFri 3/17/00Fri 3/24/00willoughby0%
10Acquisition Processing1 dayWed 5/24/00Wed 5/24/00 0%
11Purchase CFX Tasc Flow1 dayWed 5/24/00Wed 5/24/00willoughby,Lee0%
12Purchase Fluent1 dayWed 5/24/00Wed 5/24/00willoughby,Lee0%
13Purchase Bladegen Turbogen1 dayWed 5/24/00Wed 5/24/00willoughby,Lee0%
14Purchase Catia 4.21 dayWed 5/24/00Wed 5/24/00willoughby,Lee0%
15MSU TRAINING99 daysWed 5/31/00Mon 10/16/00 19%
16Flotran Training4.5 daysWed 5/31/00Tue 6/6/00willoughby,Doss0%
17ANSYS8 daysThu 10/5/00Mon 10/16/00willoughby,Doss0%
18Fluent Training5 daysWed 5/31/00Tue 6/6/00Lee100%
19CFX Tasc Flow Training5 daysMon 7/31/00Fri 8/4/00Doss,Lee0%
20Blade Gen Training4 daysTue 9/26/00Fri 9/29/00Lee,Doss0%
21MSU and B&D FTP Testing28 daysFri 6/2/00Tue 7/11/00 0%
22Transfer Files To MSU6 daysFri 6/2/00Fri 6/9/00willoughby,Tanorah0%
23 6 daysMon 7/3/00Mon 7/10/00willoughby,jack0%
24Student CFD Development1 dayMon 7/10/00Tue 7/11/00willoughby,Doss,Lee0%
25List/Install Theoretical Needs 12 daysFri 5/12/00Mon 5/29/00 0%
26Flotran7.2 daysFri 5/12/00Mon 5/29/00Team,Lee,willoughby,Doss0%
27IBM Catia 4.212 daysFri 5/12/00Mon 5/29/00Lee,willoughby,Doss0%
28CFX TASC FLOW ,BG12 daysFri 5/12/00Mon 5/29/00Lee,willoughby,Doss0%
29Ensight12 daysFri 5/12/00Mon 5/29/00Lee,willoughby,Doss0%
30List/Install Experimental Needs8.5 daysWed 5/24/00Mon 6/5/00 0%
31Swirl machine particle trace2.5 daysTue 5/30/00Thu 6/1/00Lee,Ylui0%
32Analization Chamber8 daysWed 5/24/00Fri 6/2/00Lee,Ylui0%
33Three Dimensional LAG Geometry1.5 daysFri 6/2/00Mon 6/5/00Lee,Ylui0%
34Software Analysis371 daysMon 6/19/00Mon 11/19/01 0%
35Set-Up Of Two-D Simulation1 dayFri 9/1/00Fri 9/1/00Team0%
36Develop X-SEC. Surface6 daysMon 6/19/00Fri 10/6/00Team0%
37Mesh 2-D Geometry2 daysWed 9/27/00Thu 9/28/00Team0%
38Postprocess With Solver3 daysWed 10/4/00Fri 10/6/00Team0%
39Analize/Compare Results1 dayMon 10/9/00Mon 10/9/00Team0%
40Set-Up Of Three-D Simulation14 daysTue 10/10/00Fri 10/27/00Team0%
41Develop Geometry Full Body1 dayMon 10/29/01Mon 10/29/01Team0%
42Mesh 3-D Geometry5 daysMon 11/6/00Fri 11/10/00Team0%
43Postprocess With Solver5 daysMon 11/13/00Fri 11/17/00Team0%
44Analize/Compare Results1 dayMon 11/19/01Mon 11/19/01Team0%
45Hardware Analysis14 daysTue 11/21/00Fri 12/8/00 0%
46Evaluate System Solution Options3 daysTue 11/21/00Thu 11/23/00Team0%
47Clear Housing Prototypes Delivered(MSU)1 dayTue 11/21/00Tue 11/21/00Team0%
48LDPA Prototype3 daysMon 11/27/00Wed 11/29/00Team0%
49PIV Prototype2 daysTue 11/28/00Wed 11/29/00Team0%
50Calculate Airflow and Heat Transfer1 dayThu 11/30/00Thu 11/30/00Team0%
51Compare Experimentaion With CFD Output Models6 daysFri 12/1/00Fri 12/8/00Team0%
52Literature Search On Power Tool10 daysMon 12/11/00Fri 12/22/00 0%
53Noise/Vibration5 daysMon 12/11/00Fri 12/15/00Team0%
54Particulate Flow5 daysMon 12/18/00Fri 12/22/00Team0%